THE SEDIMENTATION AND DREDGING OF GUANTING RESERVOIR

XiaoqingYang YangShanzhengLiShiqiZhang

2003Acta Scientiarum Naturalium Universitatis SunyatseniEnvironmental Science被引 2

出版方页面 →

摘要

The main tasks of the Guanting Reservoir on the Yongding River were flood control and water supply to Beijing. However, it is not able to supply water due to the serious sedimentation and water pollution in recent years. Of the total original reservoir storage capacity of 2.27×109 m3 (after rebuilt), 0.651×109 m3 in the Yongding Zone is lost due to sedimentation and 0.252×109 m3 in the Guishui Zone cannot be used due to the sand bar at the mouth of the Guishui River. Dredging is performed to deal with the sedimentation of Guanting Reservoir. A dredged channel on the mouth bar between the two parts of the reservoir, i.e. Yongding Zone and Guishui Zone, to resume their connection and a dike to guide most sediment from upstream of the Yongding River to the Guishui Zone are suggested.

引用本文(GB/T 7714)

Xiaoqing, Yang Yang, Shanzheng, 等. THE SEDIMENTATION AND DREDGING OF GUANTING RESERVOIR[J]. Acta Scientiarum Naturalium Universitatis Sunyatseni, 2003.

引文网络

参考文献与被引分析加载中…

本站仅收录题录与摘要供学习参考,全文版权归属出版方;如有侵权请联系我们删除。