An Efficient Approach for Fuzzy Project Network Analysis

HUJing-song

2002Acta Scientiarum Naturalium Universitatis SunyatseniDecision Sciences被引 1

出版方页面 →

摘要

In this paper we present two-level linear programming method for determining latest dates and slack times in project network models with triangular fuzzy number or trapezoidal fuzzy number. Compared with the well-known fuzzy network techniques in literature, the approach always produces the meaningful latest dates and slack times. Practically we have generalized critical path method by accepting imprecise,fuzzy data for the duration of the activities.